AI’s Speculative Power Demand Risks Higher Consumer Bills

The AI boom is fueling a “bubble” of speculative electricity demand from data centers, leading utilities to over-plan for new power plants. This widespread practice risks leaving ordinary consumers to pay for unneeded infrastructure through higher bills.

By
LNGFRM Team
Published November 18, 2025
"A construction site featuring the steel frame of a large building under construction, with workers on the beams and a crane in the background. In the foreground, concrete culverts are laid out on reddish-brown dirt, next to a water truck."
Image courtesy of Business Insider

The quiet hum of servers powering the artificial intelligence revolution is about to get very loud on your electric bill.

Across the United States, a peculiar kind of AI bubble is inflating, not in venture capital valuations or tech stock prices, but in the very infrastructure that keeps our lights on.

It’s a bubble of speculative demand for electricity, driven by the AI boom, and it threatens to leave ordinary consumers footing the bill for power plants that may never be truly needed.

At the heart of this unfolding drama are the nation’s utilities, the entities responsible for delivering power to our homes and businesses.

They are currently lobbying regulators for massive spending increases on new power plants and grid infrastructure, citing sky-high projections for future electricity demand.

The culprit? An explosion of proposed data centers, each voraciously hungry for power to fuel the next generation of AI.

The problem, however, isn’t necessarily the genuine need for power, but a systemic flaw in how that demand is being forecasted and managed.

Joseph Dominguez, CEO of Constellation Energy, offers a telling analogy: “You put a bunch of lines in the water to try to catch fish.” This is precisely what data center developers are doing.

A single developer, planning for one new facility, might submit electricity requests to five different utilities across various states – from Georgia to Texas and up to Minnesota.

Each utility, blind to the other requests, then initiates plans to meet this perceived demand.

Imagine the scenario: if each of those five utilities proceeds with building a new power plant to accommodate the potential data center, consumers in those regions could end up paying for five plants when only one, or perhaps none, are ultimately required.

By the time the developer settles on a final location, the other four utilities are left with expensive, underutilized infrastructure, and the costs are socialized among their existing residential and commercial customers through increased rates.

This “fishing expedition” approach is not a fringe practice; it’s widespread, and experts are sounding the alarm.

“They have a structural incentive to forecast demand growth in excess of what it is in order to recoup more returns,” explains Mark Dyson, a managing director with the Rocky Mountain Institute, a nonprofit dedicated to sustainable energy solutions.

This structural bias, coupled with the speculative nature of data center development, creates a volatile cocktail for consumer finances.

Jeremy Fisher, a principal advisor to the Sierra Club with extensive experience in energy resource planning, warns, “There’s a real risk that we’re already paying for some of that speculative load, or will be paying for that shortly.”

The scale of the disconnect is staggering.

McKinsey estimates that global data centers will require 219 gigawatts (GW) of electricity by 2030.

Yet, a Sierra Club compilation reveals that 26 of the largest investor-owned utilities in the US alone are forecasting data center projects that will demand a colossal 711 GW – nearly the total power demanded by the entire continental US at its summer peak.

Why such a colossal disparity?

Part of the answer lies in the complex ecosystem of the AI boom.

Major tech players like Amazon, Google, Microsoft, and Meta aren’t directly constructing most data centers.

Instead, a sprawling network of middlemen, from mom-and-pop operators to established real estate developers, are scrambling to build and flip these properties.

Each of these players, hoping to secure a slice of the AI pie, submits their project plans and associated power requests to multiple jurisdictions.

Astrid Atkinson, cofounder of grid efficiency software provider Camus Energy and a former Google data center engineer, estimates that the demand to connect to the grid could be five to ten times higher than the number of data centers actually built.

“Any developer is going to want to have a few options,” she notes, acknowledging that many of these prospective sites simply won’t materialize.

While some, like Ryan Mallory, CEO of Flexential, a data center operator backed by Morgan Stanley, decry the “carpet bombing markets” approach of newer developers, the practice persists, creating “a tense situation for everybody.”

Adding another layer of absurdity to this situation is the fundamental lack of the very components that make AI possible: semiconductor chips.

Nvidia and AMD graphics processing units (GPUs) are the backbone of AI computing and typically account for over half a data center’s energy use.

Enverus, an energy market data analysis firm, projects that enough GPUs will be produced to power 5 GW of computing this year, growing to 9.5 GW by 2028.

Even doubling that for cooling and other operations, that’s only around 19 GW of power demand.

“That sort of quantity is extremely detached from what the queues are suggesting,” says Carson Kearl, an analyst at Enverus.

Simply put, there aren’t enough chips in the world to utilize the power utilities say they need to provide.

For utilities, data centers represent a tantalizing growth opportunity after decades of flat or declining electricity demand due to efficiency gains.

Researchers at the Lawrence Berkeley National Lab found that data centers consumed 4.4% of total US electricity in 2023, a share that could climb to 12% by 2030.

The question isn’t whether more power is needed, but how much, and how responsibly it’s being planned.

Regional data highlights the urgency.

The Electric Reliability Council of Texas (ERCOT) added nearly 37 GW to its five-year forecast, while the PJM Interconnection, covering parts of 13 states including Virginia’s “Data Center Alley,” added over 15 GW.

These forecasts, aggregated from individual utilities, have historically shown an upward bias, overestimating demand by an average of 23% between 2012 and 2023.

John Wilson, Vice President at Grid Strategies, acknowledges this bias but also points to the difficulty of forecasting such novel, large, and uncertain loads with traditional methods.

Some utilities are proceeding with caution.

Dominion Energy, serving Virginia’s data center heartland, discounts more speculative requests, differentiating between its 54 existing data center customers and another 50 or so “speculative customers” with little substantive experience.

“It’s just competition, everybody competing for a growing slice of the pie,” a Dominion representative noted in a recent hearing.

However, others are pushing forward.

Louisville Gas and Electric and Kentucky Utilities, for example, based a request to spend $3 billion on two new gas plants on 6 GW of data center demand, despite only one of 18 projects in their service area having a “high probability” of locating there, and none having signed a contract.

State officials signed off on the expansion in October.

The good news is that regulators are beginning to wake up to this potential for “cross-subsidization,” where existing customers effectively subsidize the speculative growth of the AI industry.

Ohio’s public utilities commission approved a landmark settlement requiring data centers to pay for at least 85% of the electricity they request, even if they use less.

The impact was immediate: American Electric Power Ohio, which had cited 30 GW of demand during the rule-making process, saw requests drop to less than half that – 13 GW – after the new rules took effect.

This Ohio settlement is a harbinger of change, with at least 20 similar “large load tariffs” now under consideration across the US.

But the financial repercussions are already being felt.

Customers buying electricity from the PJM grid face an additional $7.3 billion for electricity due to data center concerns, pushing future electricity supply auction prices to a record $16.1 billion this year.

The AI revolution promises incredible advancements, but its unchecked energy appetite, fueled by speculative forecasts and systemic incentives, threatens to impose a hidden tax on every electricity consumer.

Without robust regulatory oversight and smarter, more realistic planning, the invisible AI bubble could burst not in Silicon Valley, but in our household budgets.

The shift in Ohio signals a crucial step towards accountability, but the race is on to ensure that the future of AI doesn’t come at an unreasonable and unnecessary cost to us all.

Author

  • LNGFRM Team

    Frank DiBernardo handles LNGFRM's Foodie and Miscellaneous writing tasks. He's always getting ideas from users, so don't be afraid to send an email to the editor.

Daily Newsletter
Subscribe to our Newletter!
You May Also Like
© 2026 LNGFRM. All rights reserved.